Atatürk Dam and Hydroelectric Power Plant

Quote
c831eb53-c3b9-4057-af85-efb343dff859.jpeg

Atatürk Dam and Hydroelectric Power Plant

Location

Diyarbakır

Adıyaman

Şanlıurfa

Construction Start Date

1983

Water Impoundment Start

13 January 1990

Official Opening

25 July 1992

Installed Capacity

2,400 MW

Annual Electricity Generation

8.9 billion kWh

Storage Capacity

48.7 billion cubic meters

Area Covered

817 km²

Irrigated Area

800,000 hectares

Annual Economic Contribution

1.7 billion US dollars

Atatürk Dam and Hydroelectric Power Plant (HPP) is the largest dam constructed under Türkiye’s Southeastern Anatolia Project (GAP). Located on the Euphrates River, this dam spans the provinces of Adıyaman, Şanlıurfa and Diyarbakır. It serves both for electricity generation and irrigation and is the largest dam in Türkiye and Europe.


Atatürk Dam and Hydroelectric Power Plant (HPP) - (EÜAŞ)

History and Construction Process

Construction of Atatürk Dam began in 1983 and water impoundment started on 13 January 1990. The official inauguration took place on 25 July 1992 in a ceremony attended by then President Turgut Özal and Prime Minister Süleyman Demirel. The dam’s hydroelectric power plant consists of eight turbines, with the last turbine commissioned on 10 September 1994.

Technical Specifications

  • Installed Capacity: 2,400 MW
  • Annual Electricity Generation: 8.9 billion kWh
  • Dam Embankment: Rockfill type, 169 metres high
  • Storage Capacity: 48.7 billion cubic metres
  • Surface Area: 817 km² (Türkiye’s largest artificial lake)
  • Flood Control Volume: The third largest in the world by flood control volume and sixth largest by embankment fill volume.

Economic Contributions

The economic contributions of Atatürk Dam to Türkiye are as follows:

  • Energy Production: Since 1992, it has generated approximately 210 billion kWh of electricity, contributing 500 billion Turkish lira to the economy.
  • Agricultural Irrigation: It enables irrigation of 800,000 hectares, accounting for 10% of Türkiye’s total economically irrigable land. Irrigation activities began in 1995 and currently cover approximately 450,000 hectares.
  • Annual Economic Contribution: Combined hydroelectric generation, agricultural irrigation and flood control functions are estimated to contribute approximately USD 1.7 billion annually to Türkiye’s economy.

Environmental and Social Impacts

The lake created by Atatürk Dam has also generated significant opportunities in aquaculture, tourism and water transport. Fish farming is practiced in the lake, particularly of carp species. Additionally, the dam region welcomes approximately 50,000 tourists annually.

Significance and Future Perspective

Atatürk Dam is Türkiye’s largest hydroelectric power plant and provides 10% of the country’s total hydroelectric generation. To ensure its long-term functionality, the Keban and Karakaya Dams upstream on the Euphrates River filter sediments before they reach Atatürk Dam’s reservoir, thereby reducing siltation. This arrangement is a crucial advantage that ensures the dam will continue to operate effectively for many decades.

Bibliographies

Anadolu Ajansı. "Ekonomiye Yıllık 1.7 Milyar Dolar Katkı Sağlayan Atatürk Barajı 32 Yaşında." AA Haber, 2024. Accessed March 14, 2025.https://www.aa.com.tr/tr/ekonomi/ekonomiye-yillik-1-7-milyar-dolar-katki-saglayan-ataturk-baraji-32-yasinda/3284322

Anadolu Ajansı. "Türkiye'nin Enerji Lokomotifi: Atatürk Barajı." AA Haber, 2023. Accessed March 14, 2025.https://www.aa.com.tr/tr/ekonomi/turkiyenin-enerji-lokomotifi-ataturk-baraji/883899.

DHA (Demirören Haber Ajansı). "DSİ: Atatürk Barajı Ülke Ekonomisine Her Yıl 1.7 Milyar Dolar Katkı Sağlıyor." DHA Haber, 2024. Accessed March 14, 2025.http://www.dha.com.tr/gundem/dsi-ataturk-baraji-ulke-ekonomisine-her-yil-1-7-milyar-dolar-katki-sagliyor-2480337

Devlet Su İşleri Genel Müdürlüğü. "Atatürk Barajı Ülke Ekonomisine Her Yıl 1.7 Milyar Dolar Katkı Sağlıyor." DSİ Haber, 2024. Accessed March 14, 2025.https://www.dsi.gov.tr/Haber/Detay/13076

Elektrik Üretim A.Ş. "Atatürk HES." Accessed March 14, 2025.https://www.euas.gov.tr/santraller/ataturk-hes

Inşaat Mühendisleri Odası (İMO). "Atatürk Barajı ve Hidroelektrik Santrali." İMO Yayınları, Accessed March 14, 2025.https://www.imo.org.tr/eklenti/3297,3408pdf.pdf?0.

T.C. Ministry of Agriculture and Forestry. "Atatürk Barajı Produced 3.3 Billion Liras of Energy in 2019." Ministry of Agriculture and Forestry News, 2020. Accessed March 14, 2025.https://www.tarimorman.gov.tr/Haber/4307/Ataturk-Barajindan-2019da-33-Milyar-Liralik-Enerji-Uretildi

TRT Haber. "Atatürk Barajı'ndan 2019'da Ekonomiye 3.3 Milyar Lira Katkı." TRT Haber, 2020. Accessed March 14, 2025.https://www.trthaber.com/haber/ekonomi/ataturk-barajindan-2019da-ekonomiye-33-milyar-lira-katki-453758.html.

Author Information

Avatar
AuthorNurten YalçınJuly 14, 2026 at 5:40 PM

Discussions

No Discussion Added Yet

Start discussion for "Atatürk Dam and Hydroelectric Power Plant" article

View Discussions

Contents

  • History and Construction Process

  • Technical Specifications

  • Economic Contributions

  • Environmental and Social Impacts

  • Significance and Future Perspective