Atasu Dam and Hydroelectric Power Plant

Quote

Atasu Dam is a multipurpose dam constructed in Trabzon to provide drinking, domestic, and industry water and to generate electricity power. It was designed to meet Trabzon city’s water demand and produce hydroelectric energy.


Atasu Dam (TİSKİ)

Location and Technical Specifications

Dam is located on the Galyan Stream within the boundaries of Maçka district in Trabzon, approximately 17 km from city center.

  • Height: 118 metres (from foundation)
  • Embankment Volume: 4.65 million m³
  • Storage Capacity: 35.75 million m³

Water Supply and Energy Production

The Atasu Dam provides 91.25 million m³ of drinking, domestic and industrial water annually and generates 27.14 GWh of electricity per year through a hydroelectric power plant with an installed capacity of 5 MW.

Construction and Operation Timeline

  • Impoundment Start: 28 December 2010
  • Water Distribution Start: 15 April 2011
  • Completion Date: 27 March 2012


With the commissioning of the dam, drinking water shortages in Trabzon province were largely resolved and water quality was improved through treatment facilities. Rapid progress is also being made on the second-phase treatment facilities and water transmission lines, which are part of the ongoing project.


Atasu Dam (TİSKİ)

Significance and Contributions

The Atasu Dam is one of the most critical important infrastructure projects ensuring water security for Trabzon province. In addition to meeting the region’s drinking water needs, it contributes economically through energy production. Furthermore, it plays a critical role in public health by making significant contributions to the sustainable management of water resources.

Bibliographies

TİSKİ (Trabzon İçmesuyu ve Kanalizasyon İdaresi). "Atasu Barajı." Accessed March 14, 2025. https://www.tiski.gov.tr/icerik/detay.aspx?Id=1363.

Author Information

Avatar
AuthorNurten YalçınDecember 20, 2025 at 10:41 AM

Tags

Discussions

No Discussion Added Yet

Start discussion for "Atasu Dam and Hydroelectric Power Plant" article

View Discussions

Contents

  • Location and Technical Specifications

  • Water Supply and Energy Production

  • Construction and Operation Timeline

  • Significance and Contributions

Ask to Küre